Kalk Bay CBD Roadworks

Please be advised that the Contractor will commence with work in the Kalk Bay CBD (Section D) from Thursday, 12 April 2012. As per agreement with the business community, this work was put on hold until after the main trading season. This work will entail the adjustment of existing services and the paving and repair of footways on the mountain side between Rosmead and Windsor Roads.

The sequence of work is as follows :

1. Section between Rouxville Road and Rosmead to start on the 12th and should take two to two and a half weeks to complete.

2. Section in front of ANPA jewellers to follow once the first section above is complete.

3. Section between Rouxville and Belmont will follow once ANPA is complete.

4. Section between Belmont and Colyn to follow.

5. Last section up to Windsor to follow.

It is envisage that these works will take approximately two months to complete if there are no snags. Only one section will be worked on at a time, until complete. The Contractor will endeavour to minimise disruption and provide access to business entrances during this time.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: