Herewith an extract from the Main Road Rehabilition project’s latest newsletter :
Parking Areas
All City Council parking areas within Kalk Bay will be upgraded during Phase 2 of this project. The project team is waiting on approval to upgrade the remaining parking areas owned by Intersite. Parking areas within Phase 2 are listed below:
During the initial public participation process for Phase 2, it was requested that the Contractor reconstruct all 3 parking areas in the Kalk Bay area within the first 3 months (Jan to March 2011) of Phase 2 (Leighton Road to Kalk Bay Harbour). As such, the contract documentation was prepared accordingly. During subsequent interactions with business owners and other members of the public last year, it was strongly requested that the parking areas preferably be retained for use and reconstructed one at a time within the section in which they fall, so that all the parking areas would not be affected simultaneously.
As such, the parking area opposite the Holy Trinity Church has been closed for reconstruction. Work commenced on 31 January 2011 and is anticipated to continue for the next 3 months. During this time, the entire parking area will be reconstructed therefore no access will be possible. The public should utilise the other parking areas which are available until its completion.
Phase 2 Project Programme
Work on Phase 2 (Leighton Road to Kalk Bay Harbour) commenced on 17 January 2011.
SECTIONS | LOCATION | TIMING |
Section A (seaside) southbound | Leighton Rd to Holy Trinity Church (incl parking area next to church) | Jan to end April 2011 |
Section A to C (seaside) southbound | Holy Trinity Church to Kalk Bay Station | May to end July 2011 |
Section D (mountainside) northbound | Kalk Bay Station to Holy Trinity Church | Aug to end Oct 2011 |
Section B (mountainside) northbound | Holy Trinity Church to Leighton Rd | Nov to end March 2012 |
Download the full documents by clicking on the links below:
Newsletter 16 : Feedback regarding Phase 1 & 2 of the project