Please be advised that the following will be in operation during the December 2011 break :
1. Main Road will be open to 2 way traffic (Southbound and Northbound) from Rouxville Road from 15th December 2011.
2. The incomplete sections will be made usable for parking during the holiday period. Any asphalt work that is not complete by today, will be finalised in January 2012 and should take approximately three days to complete.
3. The section from Rouxville Road up to just south of Colyn Road will be made available for parking and dedicated line markings will indicate parking bays.
4. Rouxville Road residents to exit in a northerly direction from Rosmead Road, as exit at Rouxville Road will only be in a southerly direction.
5. The area between Cape to Cuba and the Night Haven will be available for parking (on gravel surface).
6. All side roads will have access to the Main Road.
7. Clean-up will continue into the week of 19th December 2011.
8. Limited works will occur early next week however this will be non-invasive.
9. On 15 January 2012, works will commence in Section E and continue through the CBD. Note that the Contractor has committed to minimising disruption to businesses wherever possible.
The project team thanks all residents in the Kalk Bay CBD for their patience during this trying time and wish them everything of the best over the Festive Season.